Project Goals
The “N-TRAIL” PROJECT
A trail maintenance, existing trail rehabilitation project at Rancho San Rafael Park to make an existing downhill trail sustainable and to improve overall trail quality/experience.
1 – Complete N-Trail Improvements (from top/start to tailing pile)
2 – Reroute/replace existing trail & jumps from USFS property to IMBA rock garden on the side hill



4 – Reroute x-c trails
5 - Provide signage
DESIGN / CONSTRUCTION CONSIDERATIONS
1-Resource protection (sustainable trail)
2-Minimize risks, avoid hazards
3-address needs – provide challenge, accommodate race course needs
4-improve trail experience (longer in time, length,challenge)

avoiding the fall line
outsloping tread
grade reversals
insloped turns
armoring
quality construction
resource aesthetics
provide two lines (of difficulty) w/o signage
longer in length
longer in time
signage
indicate difficulty (x or xx)
sign non-rollable features (if applicable)
promote protective equipment
work being performed with permission from WC (contact info)
1) Start / Top to end of upper rock garden
berms
turns
jumps
entry to rock garden
3) Rock Garden
grade reversals
berms
armoring
warning signage
new alignment on side slope
9) REHAB OLD ROADS / TRAILS
10) PROVIDE INFO / SIGNAGE
PROJECT STATS: Existing Ending Net
Start Elev 5300.00 5300.00 +0.00
Finish Elev 5113.00 5113.00 +0.00
Distance 1320 lf 1742 lf +422 lf (+31%)
Average Grade 14.2% 10.7% -3.5%
Course time 2:20.00 ? +
Turns/Berms 4 5 +
Jumps 2 2 +
TTF’s 1 0 +
Optional Lines 0 0 +
identify type of trail (int-expert trail)
provide continuous rollable line
provide advanced / technical options
ttf’s without signage – need filters, qualifiers
ttf’s with signs – place at features
maintain good sightlines
reduce overall speed
control speeds at trail intersections
3: ADDRESS NEEDS
provide challenge
accommodate race course needs